Answered

Revering parameter entities from manageable in production to dev

We have situation where we need to revert some of the parameter entities from manageable in production to dev. Since the process is already in production, we would like to know the consequences before we proceed and change it to manageable in dev.

Please assist me on this and let me know if any additional details needed.

Comments (2)

photo
1

Dear Balakrishnaiah,

Thank you for letting us know your questions. In this case, our recommendation would be to synchronize all the values so that the Development environment will have the same values as the Production environment prior to conversion.

For more information about this, please read the following article: https://help.bizagi.com/bpm-suite/en/index.html?where_to_manage_parameter_enti.htm#manageable.

Best regards,

Laura G

photo
1

Thank you for your answer.