Answered

define the Hijri calendar

Hi

How can I define the Hijri calendar to my project? Which is the default Hijri calendar.

Comments (3)

photo
1

Dear Mostafa,

Thank you for letting us know your questions. Although there is no way to import all the important dates from a specific calendar at one time, it is possible to define working schema and holiday schema in Bizagi Studio.

Please feel free to refer to the following articles to find out more about the steps to do that:

http://help.bizagi.com/bpm-suite/en/index.html?working_time_schema.htm

http://help.bizagi.com/bpm-suite/en/index.html?holiday_schema.htm

Best Regards,

Laura G

photo
1

Hi Laura

I want the user in the work portal to be able to select the date in the Hijri calendar

photo
1

Dear Mostafa,

We sincerely apologize for the delay in answering your post.

Unfortunately, it is not possible to include the Hijri calendar to select from the work portal as Bizagi does not support it. We would like to recommend, however, the possibility of creating a customized widget that may allow you to do that. If you are willing to try that option but don't know where to start creating widgets, you may start with this article about the widget editor: https://help.bizagi.com/bpm-suite/en/index.html?widgets_editor.htm

We apologize for the inconvenience that this situation may be causing you.

Best regards,

Laura G