In Progress

When ssigning resources the simulation does not run through the process model

I'm attempting to use the simulation feature in Bizagi Studio, while simulating through the different stages I got to the third one which is the Resource Analysis, however when I assign the defined resources the instances created at the start event do not travel into the first activity, which has the resource assigned to it. Thesteps to get to this problem were as follows:

1. Modeled the process

2. Created the resources in the resource tab

3. Assigned each resource a quantity and cost

4. Assigned the necessary resources to each activity

5. Defined the scenario

6. Run the simulation.

The simulation simply does not show any numeric values when it encounters the first activity that needs a resource.

I'll attach two files one showcasing the scenario where resources are assigned, and one where no resources are assigned.

What can I do to fix this?

Best regards, Raoul

Comments (4)

photo
1

Dear Raoul,

Thank you for letting us know about this issue. This is likely a bug, so we will escalate it to the Development team so that they may take a look at it.

Best regards,

Laura G

photo
1

Dear Laura,

I'm facing the same problem. Is it fixed or not yet? What can I do?

photo
1

It is not fixed yet! I have downloaded "Simulation_example_Technical_support.bpm" demo model, filled in all atributes by BIZAGI, but not running the "resource..." and "calendar level.." But I am in teh demo mode.

photo
photo
1

Same problem!