Hi,

Consider the image scenario, I have a process with a main form, three Service tasks and a approval task. Expressions to decide which service tasks should be executed were well defined and web services are executed as expected.

When services finish, for each route opened, a new instance in the Approval task is started. I have to ask if that behavior is correct and, if the answer is yes, How to avoid the actor works more than once in the same task?

Thanks

Comments (2)

photo
1

forget the previous image

photo
1

Dear Cesar,

You need to enter to the process modeler and click on the gateway properties. On the Runtime tab, select inclusive gateway.

Inclusive Gateways must be defined in pairs if they are going to be synchronized. One Inclusive Gateway (divergent element) must be defined to activate the paths and another Inclusive Gateway (convergent element) to synchronize them.

For further information: http://help.bizagi.com/bpm-suite/en/index.html?gateways.htm

Regards