Answered

Simulation Results the number of "Instance Completed" is 0.

When I run a Level 1 simulation the "Simulation Results" screen displays the number of "Instance Completed" is 0.

Comments (1)

photo
1

Dear Munirah,

We have reviewed your issue and believe the cause is due to the timing of your tasks. For example, if

the total time for the process is 60 minutes and you have 2 tasks that take 40 minutes each, the process will

terminate at the 60 minute mark resulting in the 0 instance completed number.

Please take a look at this article: http://help.bizagi.com/process-modeler/en/level_2_example.htm

If you have any other questions please let us know.

Regards