Solved

Resource and Calendar Analysis work incorrectly

In Professional Bizagi Modeler 3.7.0.107 the Resource Analysis and Calendar analysis work incorrect. The results of Run is only 0, at the same time results of What-if Analysis are not 0 values. The Resources are assigned to tasks and their calendars are defined.

Comments (1)

photo
1

Dear Mariia,

The first recommendation that we can give you is to download and install the latest version with some fixes corrected. Here we share the download URL: https://bizagi.sharefile.com/d-s2e0c7ec2f014bbb9

We just tried running the time and resources analysis for the Vacation Request process (this process is available at the Xchange https://www.bizagi.com/platform/xchange) and the results have been different to zero.

If after the upgrade the problem still persists please attach some screenshots or a short video showing us the resources defined at the Home tab of Bizagi Modeler and also the Resources scenario that you're configuring for the simulation.

Best regards.